Detailed vision of
2012 related to hydro power |
Hydroelectricity is clean energy
and its generation is not linked to issues concerning
fuel supply, especially the price volatility of imported
fuels. It enhances our energy security and is ideal
for meeting the peak demand. Its share has gradually
declined. Therefore, thermal generation, which should
generally be used for base load operation, is also
being used to meet peaking requirements. This leads
to non-optimal utilisation of economic and perishable
resources.
|
Only about 17% of vast hydel potential
of 1,50,000 MW has been tapped so far. Countries like
Norway, Canada, Brazil have all been utilising more
than 30% of their hydro potential wherease India and
China have lagged far behind as can be seen in the
table below.
|
Therefore, exploiting the vast
hydro potential has been provided extra thrust in
the capacity addition plans and has been accorded
high priority in our power development plans. In order
to improve the themal-hydro mix following measures
have been undertaken:
|
Country
|
Exploitable
Potential(MW) |
Installed
Utillised (MW) |
%of
Potential Capacity |
Norway |
47,000 |
27,360 |
58 |
Canada |
160,000 |
65,678 |
41 |
Brazil |
170,00 |
52,427 |
31 |
China |
310,000 |
56,000 |
18 |
India |
150,000 |
23,488 |
17
|
|
|
|
|
Policy measures |
The
Union Ministry of Power has taken several steps to accelerate
capacity addition from hydro-electric projects. These
include: |
-
higher budgetary
allocation for the hydel sector.
-
investment
approval of new hydro-electric projects;
-
identification
of new projects in the Central Sector for advance
action;
-
promoting
State Sector projects which were languishing or
could not progress due to Inter-State disputes;
-
improving
tariff dispensation for hydel projects;
-
simplification
of procedure for transfer of clearance;
-
levy of 5%
development surcharge to supplement resources for
hydro electric projects by NHPC allowed by CERC.
|
Basin-wise Policy |
The policy measures undertaken
to accelerate hydro power development inter-alia lay
emphasis on basin-wise development. World Bank assistance
for survey, investigation and preparation of DPRs
of the projects in Sutlej and Ravi basins is being
considered.
|
States with
substantial undeveloped Hydro potential |
Region/State
|
Assessed
(MW) |
In
Operation (MW) |
Under
Construction |
Balance
(MW) |
Arunchal
Pradesh |
50328.00 |
10.50 |
405.00 |
49912.50 |
U.P.
/Uttaranchal |
18898.00 |
1609.85 |
3453.00 |
13835.15 |
Himachal
Pradesh |
18820.00 |
3822.95 |
1926.00 |
13071.05 |
Jammu
& Kashmir |
14146.00 |
1394.25 |
469.00 |
12282.75 |
Sikkim |
4286.00 |
84.00 |
519.00 |
3683.00
|
Karnataka |
6602.00 |
2789.40 |
222.00 |
3590.60 |
Meghalaya |
2394.00 |
185.20 |
0.00 |
2208.80 |
Mizoram |
2196.00 |
0.00 |
60.00 |
2136.00 |
M.P./
Chhattishgarth |
4485.00 |
898.50 |
30.25 |
1684.25 |
Kerala |
3514.00 |
1799.50 |
30.25 |
1684.25 |
West
Bengal |
2841.00 |
300.50 |
936.00 |
1604.50 |
Manipur |
1784.00 |
105.00 |
90.00 |
1589.00 |
Nagaland |
1574.00 |
75.00 |
24.00 |
1475.00 |
Orissa |
2999.00 |
1837.50 |
66.00 |
1095.50 |
|
|
Ranking Studies |
The CEA in consultation with
the States, Department of Space, Ministry of Environment
& Forests, CWC and Geological Survey of India, has
initiated a basin wise ranking study of all the balance
hydro sites with a view to identify those hydro projecdts
which could be taken up first so that hydro power development
is taken up in a appropriate sequence. The objective
of the study is to optimally utilise the potential of
feasible hydro projects in the country over the next
few decades. |
Preparation of Detail
Project Report |
With
the objective of reducing the time and cost overrun
of hydro projects which has largely taken place on account
of poor and hasty investigation and non-availability
of proper infrastructure in terms of access roads and
land, the Govemment has recently introduced a three
stage process for development of new hydro electric
projects in the Central Sector. The three Stages are:
|
Sector I - Survey & investigation
and preparation of prefeasibility report. |
Stage II - Detailed investigation,
preparation of DPR and pre-construction activity
including land acquisition. |
Stage III - Execution of the
project after investment decision through PIB/CCEA |
|
In
terms of the guidelines of three stage clearance and
delegation of powers approved in consultation with Ministry
of Finance and Ministry of Environment & Forests,
the Ministry of Power has been authorised to sanction
expenditure of Rs. 10 crores on survey, investigation
and preparation of feasibility report for new hydro-electric
projects. Expenditure upto Rs.50 crores can be incurred
on the preparation of DPR, pre-construction activities
and land acquisition subject to approval by a Committee
of PIB based on the site clearance from Ministry of
Environment and Forests and after the commercial viability
of the project has been established. Proposals involving
expenditure above Rs.50 crores would require approval
of PIB/CCEA. |
The
Ministry of Environment & Forests has also simplified
the procedure for according site clearance in two stages.
In Stage-I, preliminary site clearance will be accorded
to proceed with survey and investigation and preparation
of pre-feasibility report. The final site clearance
(Stage-II) will be accorded based on data made available
from survey and investigation carried out and the findings
at the pre-feasibility stage. The final forest clearance
and environmental clearance will be accorded on the
basis of Environmental/Forest Impact Assessment Study
(EIA) and Environment Management Plan. |
VI CENTRAL GOVERNMENT INCENTIVES
/FINANCES AVAILABLE
|
Ministry of Non-Conventional
Energy Sources, Govt of India. |
In
order to provide a greater thrust for speedy development
of hydro power sector, the new hydro power policy was
announced by Govt. of India (Ministry of Power) in August,
1998, which recognized the role of Ministry of Non-conventional
Energy Sources (MNES), Govt. of India in this sector.
Accordingly the subject matter of SHP projects upto
25 MWs has been transferred to MNES from Ministry of
Power w.e.f. 29th November, 1999. The incentives provided
by MNES Govt. of India under its SHP policy 2002-03,
interalia, are as under : |
Detailed
Survey & Investigation and preparation of Detailed
Project Report |
1.75 lacs INR
(upto 1 MW) |
3
lacs INR
(1-10 MW) |
5
lacs INR
(10-25 MW) |
|
|
Subsidy scheme for
setting up of commercial SHP Projects upto 25 MW station
capacity by Private, Joint Sector and others.
|
Upto 100 KW
|
101
KW-999KW |
1
MW-25 MW |
45%
of project cost limited to 30,000 INR/KW
|
45%
of project cost limited to 30 lacs INR +
21625 INR/KW |
45%
of project cost limited to 2.25 Cr. INR
+ 37.5 lacs INR/MW |
|
|
Indian Renewable Energy
Development Agency (IREDA) |
In addition to the above, IREDA
which is the financial arm of the MNES, Govt. of India
established to promote, develop and finance renewable
energy technologies and provides funding for development
of SHP for setting up commercial SHP projects upto 25
MW station capacity by Private, Joint Sector & others
on the following financial terms : |
Term Loan
|
- Upto 75% of project cost
(upto 1 MW capacity)
- Upto 70% of project cost (1-25
MW capacity)
|
Interest
Rate |
- 11.25% upto 1 MW
- 11.50% above 1 MW upto 5 MW
- 11.75% above 5 MW upto 15 MW
- 12.00% above 15 MW upto
25 MW
|
Repayment
Period |
- Maximum 10 years repayment
- Maximum 3 years grace period
- Quarterly installments
|
http://www.visionri.net/article.asp?article=resources-energy-hydropower |
|